Adelaide, Dec 23, 2009 (ABN Newswire) - Beach Energy Limited (ASX:BPT) (PINK:BEPTF) drilling report for the week ending 23 December.

Highlights of the week's activities include:

Cooper Basin (South Australia/Queensland) - Oil Drilling

Oil development wells Narcoonowie-8 (Beach 20,21%) and Tickalara-21 (Beach 30%) were cased and suspended as successful oil wells during the week.

A Drill Stem Test conducted in Narcoonowie-8 over the Birkhead interval 1613 - 1620 metres yielded 50.4 barrels of clean oil and 2.4 barrels of drill mud in a 4 hour flow period.

.

--------------------------------------
Well                    Participants
--------------------------------------
Burke-11                BPT     20.21%
PPL 12                  STO*    66.60%
Gas Development         ORG     13.19%
C/E Basin, SA
-------------------------------------------------------
Weekly Progress & Summary              Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs(CST)23/12/2009   Epsilon Formation,
Depth:       2581m (TD)                 Patchawarra Formation
Operation:   Well is cased and suspended as
             a future Toolachee, Daralingie
             and Patchawarra Formations gas producer.
Progress:    77m

--------------------------------------
Well                    Participants
--------------------------------------
Narcoonowie-8           BPT     20.21%
PPL 114                 STO*    66.60%
Oil Development         ORG     13.19%
C/E Basin, SA
-------------------------------------------------------
Weekly Progress & Summary              Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs(CST)23/12/2009   Birkhead Formation,
Depth:       1684m (TD)                 Murta/McKinlay
Operation:   Well is cased and suspended
             as a future Birkhead Formation
             oil producer.
Progress:    742m

--------------------------------------
Well                    Participants
--------------------------------------
Tickalara-21            BPT     30.00%
PL 34                   STO*    70.00%
Oil Development
C/E Basin, QLD
-------------------------------------------------------
Weekly Progress & Summary              Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs(CST)23/12/2009   McKinlay Member,
Depth:       1446m (TD)                 Namur Sandstone
Operation:   Well is cased and suspended as
             future Murta Formation, McKinlay
             Member and Namur Sandstone oil producer.
Progress:    29m

--------------------------------------
Well                    Participants
--------------------------------------
Tickalara-22            BPT     30.00%
PL 34                   STO*    70.00%
Oil Development
C/E Basin, QLD
-------------------------------------------------------
Weekly Progress & Summary              Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs(CST)23/12/2009   McKinlay Member,
Depth:       153m                       Namur Sandstone
Operation:   Running surface casing.
Progress:    153m

(s)  Secondary Targets
(*)  Operator
BPT  Beach Energy Ltd
ORG  Origin Energy Resources Ltd
STO  Santos Limited


About Beach Energy Limited

Beach Energy Limited (ASX:BPT) is a long established oil and gas Exploration and Production Company, based in Adelaide, South Australia.

Contact

Hector Gordon
Chief Operating Officer
TEL: +61-8-8338-2833

  Related Companies

>>>              Beach Energy Limited
>>>              Origin Energy Limited
>>>          Santos Limited

  Related Industry Topics:

Gas & Oil | Energy General | Financial General | 

  This Page Viewed:  (Last 7 Days: 10) (Last 30 Days: 20) (Since Published: 23190) 

Events & Exhibitions

Site Search

 
 ENGLISH   All Languages

Upcoming WebCasts

Mr Mark Paton CEO
Cue Energy Resources
Tuesday, June 12, 2012

Mr Alan Hopkins CEO
Pan Asia Corporation
Tuesday, June 12, 2012

Mr Barry Dawes
Martin Place Securities
Tuesday, June 12, 2012

Dr Andrea Grant CEO
Living Cell Technologies
Monday, July 02, 2012


Beach Energy Limited
2012.05.25  13:47 Beach Energy Limited (ASX:BPT) Progressing Tie-In of New Oil Trunkline to Moomba
2012.05.21  15:51 Beach Energy Limited (ASX:BPT) To Accept Cooper Energy (ASX:COE) Off-Market Takeover Offer For Somerton Energy (ASX:SNE)
2012.05.15  16:53 Beach Energy Limited (ASX:BPT) Clarification of Dow Jones Article
2012.05.02  15:33 Beach Energy Limited (ASX:BPT) Monthly Drilling Report - April 2012
2012.04.30  10:09 Beach Energy Limited (ASX:BPT) Quarterly Activities Report to 31 March 2012
Origin Energy Limited
2012.01.09  10:32 Beach Energy Limited (ASX:BPT) Commences Production from Middleton Gas Project
2011.02.23  12:05 Australian Market Report of February 23, 2011: Origin Energy (ASX:ORG) Announce Government Approval For Liquefied Natural Gas Joint Venture Project In Queensland
2011.02.09  11:07 Beach Energy Limited (ASX:BPT) Announce Prospective 18% Reserves Increase For Cooper Basin Joint Venture
2010.07.22  00:00 Adelaide Energy Limited (ASX:ADE) Releases Fourth Quarter Activities Report Ended 30 June 2010
2010.07.07  12:30 Beach Energy Limited (ASX:BPT) Monthly Drilling Report For June 2010
Santos Limited
2012.05.25  13:47 Beach Energy Limited (ASX:BPT) Progressing Tie-In of New Oil Trunkline to Moomba
2012.01.24  09:55 Richard Cottee Joins Austin Exploration (ASX:AKK) Board As Non Executive Chairman
2012.01.09  10:32 Beach Energy Limited (ASX:BPT) Commences Production from Middleton Gas Project
2012.01.04  16:12 Beach Energy Limited (ASX:BPT) Monthly Drilling Report - December 2011
2011.11.22  10:07 Beach Energy Limited (ASX:BPT): Tantanna Pipeline Back Online
Webcast Your Annual General Meeting

Mobile Video TV

qrcode
Scan with your Mobile Phone to view ABN Newswire Video Channel on Mobile
 
City Index - A Better Way To Trade