Sydney, Oct 4, 2011 (ABN Newswire) - Iron Road Limited (ASX:IRD) is pleased to advise that the first traverse of Central Eyre Iron Project Stage IV drilling at Hambidge confirms significant thickness of magnetite gneiss.

Summary

- The Stage IV Drilling Programme successfully tested several selected targets across E3699 based on the interpretation of a detailed aeromagnetic survey.

- Hambidge Stage IV drilling was delayed due to the higher priority Stage V and VI drilling programmes at Murphy South.

- Two diamond rigs are currently drilling at Hambidge with Traverse D now complete.

- Drill holes intersected continuous magnetite gneiss of up to 200m apparent thickness.

- Hambidge is believed to have the potential to rival Murphy South in size and tonnage.

Progress to date
-------------------------------------------
Hole Type          Metres (m)   Holes (No.)
Diamond (planned)   5,600        12
Diamond (completed) 1,482        3
-------------------------------------------

The Stage IV drilling programme at Hambidge comprises an initial 12 diamond drill holes for 5,600m. Completion of all 12 holes will allow for the estimation of an exploration target for the area.

For the Full Announcement click:
http://media.abnnewswire.net/media/en/docs/ASX-IRD-559911.pdf


About Iron Road Limited

Iron Road Limited (ASX:IRD) is an Australia-based company. The Company is engaged in exploration and evaluation of its iron ore ground holdings. Its projects include the Central Eyre Iron project, Gawler Iron project and Windarling Iron project. The Central Eyre Iron Project consists of three distinct prospects: Warramboo, Kopi and Hambidge. The Company focuses on establishing a resource inventory that underpins a 5 to 10 metric tons per annum (Mtpa) magnetite export operation. It contains magnetite-bearing gneiss units with a cumulative strike length. Gawler Iron project includes over ten areas of known iron occurrences, including the Mt Christie deposit. A total of 252 in-situ rock chip and grab samples from 10 localities at the West Gawler project returned an average grade of 53.4% Fe. The Company developed a stage plan of ground work on Windarling project.

Contact

Andrew Stocks
Managing Director
Iron Road Limited
Tel: +61 8 9200 6020
Mob: +61 (0)403 226 748
Email: astocks@ironroadlimited.com.au


  Related Companies

>>>          Iron Road Limited

  Related Industry Topics:

Metals | Financial General | Mining | Iron Ore | 

  This Page Viewed:  (Last 7 Days: 80) (Last 30 Days: 430) (Since Published: 7070) 

Events & Exhibitions

Site Search

 
 ENGLISH   All Languages

Upcoming WebCasts

Mr Mark Paton CEO
Cue Energy Resources
Tuesday, June 12, 2012

Mr Alan Hopkins CEO
Pan Asia Corporation
Tuesday, June 12, 2012

Mr Barry Dawes
Martin Place Securities
Tuesday, June 12, 2012

Dr Andrea Grant CEO
Living Cell Technologies
Monday, July 02, 2012


Webcast Your Annual General Meeting

Mobile Video TV

qrcode
Scan with your Mobile Phone to view ABN Newswire Video Channel on Mobile
 
City Index - A Better Way To Trade