Enerji Limited Stock Market Press Releases and Company Profile
Second Heat Recovery Unit Installed at Carnarvon
Second Heat Recovery Unit Installed at Carnarvon

Perth, April 4, 2012 AEST (ABN Newswire) - Perth-based clean power company Enerji Limited (googlechartASX:ERJ) has successfully installed the second of the three heat recovery units (HRU) at the Carnarvon project in Western Australia.

The HRUs incorporate an Airec heat exchanger to capture the heat from the engine's hot exhaust.

The design of the system is ingenious, allowing the engine exhaust to take its usual path when the waste heat to power system (WHPS) is not in operation. When the WHPS is operational, the exhaust is diverted through the Airec heat exchanger and then channeled back to the original exhaust stack.

Recent clear conditions at Carnarvon have allowed the installation of the first two HRUs following a delay caused by a period of inclement weather. The image below shows the crane lifting the second unit into place over the top of the existing power plant.

Installation of the third and final HRU is scheduled for next week, barring any delays.

Commissioning at the Carnarvon project is now expected at the end of April.

The Carnarvon Power Station is in the Gascoyne region of Western Australia. Following installation of the WHPS by Enerji, revenue will be generated through selling the electricity created by the Opcon Powerbox. The Powerbox has the capacity to increase the power station's energy output by up to 700kW without burning additional fuel or creating emissions.

Further construction updates, highlights and milestones will be announced in due course. For more photographs documenting the installation of Enerji's first waste heat to power system go to:
http://www.enerji.com.au/index.php?option=com_content&view=article&id=261&Itemid=81

Contact

Enerji Limited
Greg Pennefather
T: +61-8-9268-3800
WWW: www.enerji.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 3) (Last 30 Days: 17) (Since Published: 4421)