Prospect Resources Ltd (ASX:PSC) (Prospect, the Company) is pleased to report on another busy quarter of activities.

Summary of Announcements:

4 July - Spodumene bearing pegmatite intersected 

6 July - 2nd drill hole intersects Spodumene bearing pegmatite 

12 July - 3rd & 4th drill hole intersects Spodumene bearing pegmatite 

19 July - Acquisition of option over God's Gift lithium project 

20 July - Prospect raises $14m in placement 

22 July - Fundraising increased to $16m 

22 July - High grade lithium oxide results 

28 July - Completion of placement 

2 August - 16 drill holes completed at Arcadia 

8 August - Additional high grade lithium results 

9 August - Completion of additional $1m placement 

16 August - Market update - Pegmatite intercepts up to 45m 

17 August - 18 RC holes completed - Pegmatites up to 51m think 

31 August - High grade assay results 

9 September - Presentation to ADU 

19 September - Very high grade assay results 

27 September - New lithium bearing pegmatite discovered 

30 September - Annual Report 

As investors can see from the above summary, the quarter consisted of project development, and fundraising.

It is worth reminding investors that Prospect only acquired the option to purchase a controlling interest in Arcadia on 12 May 2016 and we exercised that option on 14 June 2016. As previously announced, we intend to release our maiden JORC reportable Mineral Resource Estimate by 31 October - some 4 and a half months since acquiring the project. Our team really does need to be applauded for their efforts.

The Company is on track to complete its maiden JORC reportable Mineral Resource Estimate by 31 October and scoping study by 31 December in anticipation of commencement of mining by 30 June 2017.

Arcadia High Grade Lithium Project

Activities during the quarter included:

- Diamond drilling

- RC drilling

- Process Plant design

- Resource modelling

- Environmental approvals

- Metallurgical testing

- Acquisition of additional Mining Licences/claims

- Camp upgrades.

The Company's maiden JORC reportable Mineral Resource is expected to be released on Monday 31 October. Within this document will be a detailed description of the project.

Gwanda East Gold Project

Development of the Prestwood Main and Prestwood A mines had slowed in June, July and August simply due to us being a small team and resources were allocated to Arcadia. Since September a new Mine manager has been appointed and an expanded team deployed to rectifying this deficiency (now we have the financial capacity to expand). The focus has shifted back to mine development and exploration, a total of 12 holes for 2,200 metres of Diamond drilling was completed down dip of the Prestwood A and the Bucks Reef, assay results will be announced in due course. The following activities are in progress:

- Prestwood Main, shaft sinking to 6 level is now complete, cross cut development to the reef package in the hanging wall ore body is now ongoing.

- Prestwood A, head gear upgrade from an exploration to a production head gear is now complete. Shaft sinking continues to 3 level with the drives on 2 level being developed east and west on Reef.

- Sally, there is a 24 hr a day dewatering operation ongoing. A head gear is available and will be erected soon. The old stopes have been surveyed and underground development is being fast tracked. The down dip extensions to the Sally will be tested in the next round of exploration drilling scheduled for December 2016.

- Bucks Reef, access to the lower levels is being made safe to facilitate underground exploration drilling.

We have the dual focus of developing the gold mines in Gwanda East and drilling up our first JORC reportable resource at Arcadia.

Summary of Activities Planned for the Period to 31 Dec 2016:

Arcadia High Grade Lithium Project

- Drilling to continue

- Collection of bulk samples for delivering to potential off-take partners

- Continue mine planning and plant design for Arcadia in parallel with resource definition work

God' Gift Lithium Project

- Due diligence including: mapping, gridding, pitting, ground magnetics and diamond drilling

- Decision to purchase or relinquish

Gwanda East Gold Project

- Additional 2,000m exploration drilling at the Prestwood A and Sally mines

- Continue blocking out production ore blocks at Prestwood Main and Prestwood A

- Begin development of the Sally Mine, including erecting the head gear, installing power and equipping the underground

- Begin underground exploration drilling

To view the report, please visit:
http://abnnewswire.net/lnk/PA7S1C3M


About Prospect Resources Ltd

Prospect Resources Limited (ASX:PSC) is based in Australasia with operations in Zimbabwe and is a publicly listed company. We are committed to creating value for Prospect's shareholders and the communities in which our company operates. Our vision is to build a Southern African based mining company of international scale.

 

Contact

Hugh Warner
Executive Chairman
Prospect Resources Ltd
T: +61-413-621-652

Harry Greaves
Prospect Resources Ltd
Executive Director
T: +263-772-144-669
WWW: www.prospectresources.com.au



Link: Quarterly Activities Report


Related Companies

Prospect Resources Ltd
   


Related Industry Topics:

 (12423)