Genex Power Limited (ASX:GNX) (Genex or Company) is pleased to announce that it has successfully achieved solar substation energisation (Energisation) of the Kidston Stage 1 Solar Project (KS1 or Project). Energisation is a major construction milestone and also represents a significant event in the development of the Company.

- Successful energisation of the Kidston Stage 1 Solar Project substation

- AEMO registration as a Market Generator completed

- All permitting in place for electricity generation and revenue in December 2017

Energisation is one of the most important testing and commissioning steps before electricity can be exported from the Project into the National Electricity Market (NEM).

Genex is also pleased to report that it has achieved registration by the Australian Energy Market Operator (AEMO) as a Market Generator, and has thus completed all technical and regulatory processes to enable the export of electricity into the NEM.

Commenting on these significant milestones, Genex's Managing Director Michael Addison stated:

"Energisation of the solar substation is a crucial milestone in the commissioning for any large-scale renewable energy project. The smooth development of the Project to date is a reflection of the significant dedication and effort by the project delivery team. With all necessary regulatory approvals in place Genex is now able to complete the final steps to enable the dispatch of electricity into the NEM.

With first generation and revenue scheduled for early December 2017, we are pleased to reconfirm that the development remains on time and on budget.

I would also like to take this opportunity to acknowledge the support of the Commonwealth and Queensland State Governments. The Commonwealth Government, through the Australian Renewable Energy Agency, has continued to support Genex Power's Kidston Renewable Energy Hub, providing $8.9 million in funding for KS1 and up to $9 million for Stage 2. The Queensland Government, by providing a 20-year revenue support deed and by designating the Project "Critical Infrastructure", significantly contributed to the success of the Project".

About ARENA:

ARENA was established by the Australian Government to make renewable energy technologies more competitive and increase the supply of renewable energy in Australia. Through the provision of funding coupled with deep commercial and technical expertise, ARENA provides the support needed to accelerate the development of promising new solutions towards commercialisation. ARENA invests in renewable energy projects across the innovation chain and is committed to sharing knowledge and lessons learned from its portfolio of projects and information about renewable energy. ARENA has committed $1.1 billion in funding to more than 270 projects. For more information, visit http://www.arena.gov.au

To view figures, please visit:
http://abnnewswire.net/lnk/2T71KX8K


About Genex Power Ltd

Genex Power Limited is focused on developing a portfolio of renewable energy generation and storage projects across Australia. The Company's flagship Kidston Clean Energy Hub, located in north Queensland, will integrate large-scale solar generation with pumped storage hydro. The Kidston Clean Energy Hub is comprised of the operating 50MW stage 1 Solar Project (KS1) and the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro) with potential for further multi-stage wind and solar projects. The 50MW Jemalong Solar Project (JSP) is located in NSW and provides geographical diversification to the Genex Power Limited portfolio. JSP was energised in early December 2020 and commissioning is now underway. Genex is further developing its energy storage portfolio via the early stage development of a 50MW/75MWh standalone battery energy storage system at Bouldercombe in Queensland. With over 400MW of renewable energy and storage projects in development, Genex is well placed as Australia's leading renewable energy and storage company.

     

Contact

Simon Kidston
Executive Director
Tel: +61 2 9048 8850
Email: sk@genexpower.com.au



Link: Genex Achieves Energisation for Kidston Solar Stage 1


Related Companies

Genex Power Ltd
            


Related Industry Topics: