Altech Chemicals Limited (Altech/the Company) (
Highlights
- Land sub-title number (PTD number) received
- Construction development order application submitted
- Preparation of early bulk earth works underway
Altech has been advised that the development order approval time-line is typically 6-8 weeks, however the Company is working with its appointed EPC contractor SMS group GmbH and local authorities for the earlier commencement of bulk earth works and the mobilisation of various sub-contractors, to maintain project momentum.
Earlier this month (refer ASX Announcement dated 6 November 2018), the Company announced that it had finalised its HPA plant site layout and building design, a final requirement before the submission of the development order application.
About Altech Batteries Ltd
Altech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.
The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.
Contact
CorporateIggy Tan
Managing Director
Altech Batteries Limited
Tel: +61-8-6168-1555
Email: info@altechgroup.com
Martin Stein
Chief Financial Officer
Altech Batteries Limited
Tel: +61-8-6168-1555
Email: info@altechgroup.com
Related Companies
Related Industry Topics: