Brisbane, May 7, 2008 AEST (ABN Newswire) - Beach Petroleum Limited (ASX:BPT) announce the weekly drilling report for the week ending 7 May 2008. Highlights of the week's activities include:

Cooper/Eromanga Oil

Bodalla South-19 (Beach 100%) is being cased and suspended for future completion for oil production from the Birkhead Formation and Hutton Sandstone.

BMG Project

Basker-6 ST1 (Beach 30%) was perforated over three reservoir intervals with resulting oil flow rates from each zone in the range 3980-4800 bopd. The well is expected to commence production in the third quarter of 2008.
----------------------------------------------------------------------------------------------------Well            Participants            Weekly Progress & Summary                    Primary Targets----------------------------------------------------------------------------------------------------Bodalla South-19        BPT*    100.0%  Report Time:    0600 hrs (CST) 07/05/2008    Birkhead/HuttonPL 31                                   Depth:          1686m (TD)                                                              Operation:      Well to be cased                                                         and suspended as a future oilOil Appraisal                                           producer from the Birkhead                                                         Formation and Hutton Sandstone.C/E Basin, QLD                          Progress:       1686m                   DST from Basal Jurassic flowed water to surface.                                ----------------------------------------------------------------------------------------------------Basker-6 ST1            BPT     40.00%  Report Time:    0600 hrs (CST) 07/05/2008    Intra-Latrobe VIC /L26                AZA*    40.00%  Depth:          3395mRT (TD)                 sands   Dev/Appraisal (Oil)     CIECO   20.00%  Operation:      Completion operations   Gippsland                               Progress:       0m                      Well to be cased and completed as a future oil producer.                        ----------------------------------------------------------------------------------------------------Coonatie-12             BPT     17.14%  Report Time:    0600 hrs (CST) 06/05/2008    Numerous PermianPPL: 131                STO*    72.32%  Depth:          3165m (TD)                   targets   Gas Development         ORG     10.54%  Operation:      Cased and suspended as a                                                          future gas producerC/E Basin, SA                           Progress:       312m                    ----------------------------------------------------------------------------------------------------Bindah-2                BPT     20.21%  Report Time:    0600 hrs (CST) 06/05/2008    PatchawarraPPL: 124                STO*    66.60%  Depth:          2607m                        Tirrawarra (s)Oil &Gas Devel          ORG     13.19%  Operation:      Drilling ahead in the                                                         Patchawarra formation  C/E Basin, SA                           Progress:       1212m                   ----------------------------------------------------------------------------------------------------COAL SEAM GAS PROJECTS                                                          ----------------------------------------------------------------------------------------------------Location                Participants    Well          Depth   Operation: 0600hrs (EST) 7th May 2008Pl 198                  BPT     40%     Tipton-100T   570.22m Completed - Mobilised to Tipton - 25TCoal Seam Develop't     AOE*    60%     Tipton-28T        18m Drilling ahead in surface hole                                        Tipton-25      252.3m Coring ahead            Sur Basin, QLD                          Tipton-96T      4856m Drilling ahead to TD            ----------------------------------------------------------------------------------------------------ATP 683P                BPT     40%     River Road 5T    467m Completed - Mobilised to Tipton - 96TSurat Basin, Qld        AOE*    60%                                     ----------------------------------------------------------------------------------------------------* Operator                                                              **  BPT  30% subject to completion of sale of 10% equity to Sojitz                            ** SOJITZ  10% subject to completion of purchase from Beach                                   BPT   Beach Petroleum Ltd        ORG   Origin Energy Resources Ltd    STO   Santos Limited    AOE   Arrow Energy NL            AZA   Anzon Australia Ltd          CIECO = Itochu CorporationCOE   Cooper Energy Ltd       SOJITZ  Sojitz Energy Australia Ltd                                                                C/E = Cooper/Eromanga             Sur = Surat             Gip = Gippsland                 ----------------------------------------------------------------------------------------------------

Contact

Reg Nelson
Beach Petroleum
TEL: 08 8338 2833


ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 5) (Last 30 Days: 12) (Since Published: 1211)