Adelaide, Dec 31, 2008 AEST (ABN Newswire) - Beach Petroleum Limited (ASX:BPT)(PINK:BEPTF) announce the drilling report for the week ending ending 31 December 2008

The drilling report and well location map for the week ending 31 December, 2008 are attached. Highlights of the week's activities include:

Beach Petroleum Operated Cooper / Eromanga Exploration

The Callawonga-6 oil field development well (PPL 220) spudded on 27 December and is currently drilling ahead at a depth of 935m. Interests in Callawonga-6 are Beach Petroleum Ltd (75%) and Cooper Energy Ltd (25%).

Cooper/Eromanga Oil Exploration and Development - Santos Operated

In areas operated by Santos, one well was successful (Minos-1, Beach 30%) and one well is in progress (Spencer West-3, Beach 20.21%).

Beach Operated Offshore Australia Program - South East Australia

Fermat-1 is at a depth of 2807m, preparing to drill ahead after running 9 5/8" intermediate casing. Interests in Fermat-1 are Beach Petroleum Ltd, 50%, Essential Petroleum Resources Ltd, 25% and Mitsui E&P Australia Pty Ltd, 25%.

Egypt - South East July Concession - Gulf of Suez

South July-1 is at a depth of 612m in the Zeit Formation. Current operation is running 20" surface casing. Interests in South July-1 are Beach Petroleum (Egypt) Pty Limited, 20.00%, Santos Egypt Pty Ltd, 40.00% and Dana Petroleum (E&P) Limited, 40.00%.
------------------------------------Well                    Participants------------------------------------ South July-1            BPT     20.00%  SE July Concession      STO     40.00%  Oil Exploration Well    DNX     40.00%  Gulf of Suez,  Egypt                    ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600hrs (Egypt) 30/12/2008      Rudeis FmDepth:          612m                            Nubia SstOperation:      Running 20" casing.                     Progress:       441m                    ------------------------------------Well                    Participants------------------------------------ Fermat-1                BPT*    50.00%  VIC/P46                 EPR     25.00%  Gas Exploration         MIT     25.00%                      Otway Basin, Vic                        ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0800 (AEST) 31/12/2008          Waarre FmDepth:          2807m MDRT                      Flaxman FmOperation:      preparing to  drill ahead after running 9 5/8" intermediate                 casing.                 Progress:       645m                    ------------------------------------Well                    Participants------------------------------------ Callawonga-6            BPT*    75.00%  PPL 220                 COE     25.00%  Oil Development                                       C/E Basin, SA                           ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 31/12/2008       Namur SstDepth:          935m                    Operation:      Drilling ahead in the Allaru Mudstone.    Progress:       935m                    ------------------------------------Well                    Participants------------------------------------Minos-1                 BPT     30.00%  ATP 259P                STO*    70.00%  Oil Exploration                         C/E Basin, Qld                                              ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (AEST) 31/12/2008      Hutton SstDepth:          1761m (TD)                      Namur Sst (s)Operation:      Well is to be cased and         Basal Jurassic (s)                suspended as a future Birkhead /                                    Hutton oil producer.  Currently preparing to test a                 potential oil zone in the Westbourne Formation.     Progress:       527m                    ------------------------------------Well                    Participants------------------------------------ Tirrawarra-74           BPT     20.21%  PPL20                   STO*    66.60%  Gas Development         ORG     13.19%                          C/E Basin, SA                           ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 31/12/2008       Patchawarra FmDepth:          3033m (TD)                      Tirrawarra SstOperation:      Well to be cased and suspended as a future gas producer.Progress:       261m                    ------------------------------------Well                    Participants------------------------------------ Kanowana-7              BPT     23.20%  PPL 28                  STO*    60.06%  Gas Development         ORG     16.74%        C/E Basin, SA                           ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (AEST) 31/12/2008      Tirrawarra SstDepth:          1364m                           Patchawarra Fm (s)Operation:      Drilling ahead in the Early Cretaceous.           Progress:       1364m                   ------------------------------------Well                    Participants------------------------------------  Spencer West-3          BPT     20.21%  PPL 53                  STO*    66.60%  Oil Appraisal           ORG     13.19%          C/E Basin, SA                           ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 31/12/2008       McKinlay MemberDepth:          1487m                           Namur, Hutton(s)Operation:      Pulling out of hole for a bit change.           Progress:       1487m                   --------------------------------COAL SEAM GAS PROJECTS          Location            Participants--------------------------------ATP-683P                BPT     40%     Coal Seam Develop't     AOE*    60%     Surat  Basin, QLD                       --------------------------------------------------------------------Well         Depth       Operation: 0600hrs (EST) 31st December 2008--------------------------------------------------------------------Tipton- 146     250m    Surface casing run, will recommence drilling on the                5th January.            * Operator                                                              (s)  Secondary Targets                          AOE  Arrow Energy NL            EPR  Essential Peteroleum Resources Ltd         BPT  Beach Petroleum Ltd                                ORG  Origin Energy Resources LTD                MIT  Mitsui E&P Australia               STO  Santos Limited                             COE  Cooper Energy Resources            DNX  Dana Petroleum (E&P) Limited		

Contact

Reg Nelson
Beach Petroleum
08 8338 2833

Mark Lindh
Adelaide Equity
0414 551 361

Ian Howarth
Farrington National
03 9223 2455


ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 5) (Last 30 Days: 16) (Since Published: 1470)