Omni Bridgeway Limited Stock Market Press Releases and Company Profile
Backreef-1 Production Test
Backreef-1 Production Test

Melbourne, May 7, 2012 AEST (ABN Newswire) - Oil Basins Limited (googlechartASX:OBL) wishes to make the following announcement so as to keep the market fully informed.

The Company, as operator Backreef Area, wishes to advise that subject to receiving all necessary approvals and consents from the DMP to conduct the forthcoming Backreef-1 Production Tests the anticipated timetable is as follows:
Rig-up of ADS Rig#2*           15 May^Production testing             17 - 20 May^Rig-down/demobilisation        Circa 21 May^

Notes: * Site works were completed as expected on 4 May 2012. ^ Indicative and subject to change.

OBL will duly advise the market of the following:

1) When all approvals have been obtained;

2) When the ADS Rig#2 has arrived onsite; and

3) Summary of the test results at the conclusion of the Backreef-1 Production Test program.

In addition, with the significant additional costs of conducting two production tests (rather than only one as originally planned in the previous budget of $900,000) and the unforeseen additional costs associated with site works and mobilization of an appropriate camp from Geraldton (rather than Derby area), the likely revised budget is now circa $1.8 million.

Attached to this Update are the objectives of the Backreef-1 Production Test program, to view the objectives please click the following link below:
http://media.abnnewswire.net/media/en/docs/ASX-OBL-373105.pdf

Contact

Oil Basins Limited
T: +61-3-9692-7222
F: +61-3-9529-8057
WWW: www.oilbasins.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 6) (Last 30 Days: 28) (Since Published: 2590)