Sets Export Credit Finance Approval Target Date
Sets Export Credit Finance Approval Target Date

Perth, Sep 15, 2017 AEST (ABN Newswire) - Altech Chemicals Limited (Altech/the Company) (googlechartASX:ATC) (googlechartA3Y:FRA) is pleased to announce that a target date of 14 December 2017 has been set for decision making for the offer of cover by the German government inter-ministerial committee (IMC), of the application for export credit project finance cover (ECA cover).

Highlights

- Target date of 14 December 2017 set for decision making by German government interministerial committee (IMC) for German ECA cover

- Lenders due diligence is currently in the final stage

- Successful due diligence with no fatal flaws

- Expert Opinion report for Euler Hermes nearing completion

- Target date is a significant milestone for development of Altech's HPA project

A positive decision of the SMS group GmbH (SMS) and KfW IPEX-Bank ECA application will result in the award of a legally binding offer of cover by the Federal Republic of Germany for the majority of the debt portion of funding required for Altech's high purity alumina (HPA) project. The offer of cover and a separate bank approval based on a pre-negotiated debt term sheet finance package provided by KfW IPEX-Bank will position the Company to proceed to secure project equity.

The setting of the ECA cover target date also marks the successful conclusion of extensive and detailed independent project due diligence. All due diligence consultants have committed to submit final reports to the expert opinion consultant by mid-October 2017, to enable submission of the expert opinion report by 9 November 2017. At a meeting last week in Frankfurt, Germany attended by the Company and representatives from KfW IPEX-Bank; SMS; and the various due diligence consultants, it was confirmed that no fatal flaws in the project had been identified during due diligence. It was agreed by all parties that based on the successful outcome of due diligence the Company's HPA project is ready to proceed to the ECA cover final assessment for debt financing approval.

Malaysian HPA plant

The Company's German engineering, procurement and construction (EPC) contractor SMS is targeting mid-October 2017 to finalise the EPC contract price for the construction of Altech's Malaysian HPA plant. The final EPC price and HPA plant design is required for the ECA cover application to determine the final amount of project debt and equity.

The scope of work for HPA plant has changed substantially under the fixed priced turnkey EPC contract proposed by SMS. Plant capacity has been upgraded to 4,500 tonnes per annum, and at the request of financing parties, the plant design now incorporates a flexible finished product line capable of producing HPA for both the synthetic sapphire industry (4,500tpa of high density pellets) and HPA for the lithium-ion battery industry (1,500tpa of powder at sub-micron particle size). This capability was not in the original plant design or feasibility study.

As a condition of the debt financing process the project has been significantly de-risked in many areas. The plant design and scope has substantially changed in response to due diligence. Superior lining materials have been selected for equipment used at the back end of the plant (after roasting) to minimise finished product contamination risk. Whist the materials are significantly more expensive than the original design, there incorporation further de-risks the project by enhancing the plant's capacity to achieve the required 99.99% finished product purity standard. Also, plant emissions targets are now significantly more conservative compared to local requirements due to international requirements (Equator Principles and OECD Common Approaches).

Since Altech announced the results of its feasibility study in March 2016, there has been a substantial deterioration of the Euro/USD exchange rate (0.98 to 0.83). Many other "factored" construction costs such as freight, final design, contractor mobilisation and demobilisation, temporary facilities, insulation and commissioning have now been accurately costed by SMS.

The fixed price lump sum EPC contract will now include a completion guarantee with liquidated damages provisions; and throughput and process/quality guarantees supported by a substantial performance bond. All plant and equipment will be accompanied with warranty guarantees supported by a significant warranty bond. Obtaining these extensive guarantees for a chemical processing plant is an exceptional outcome that significantly de-risks the project. These guarantees were instrumental in bringing technical project due diligence to conclusion and securing the target date for the IMC meeting.

Updated capital costs and study details are expected to be available and announced in October 2017, following notification by SMS of the final EPC contract price for construction of the Malaysian HPA plant. The Company has not yet received the final executable EPC price from SMS. The Company anticipates a significant increase in debt finance and ECA cover availability in support of an expected substantial increase in the project capital cost. Modelling has demonstrated the financial robustness and attractiveness of the project over a broad range of capital costs and a variety of debt/equity combinations.

Altech's managing director, Mr Iggy Tan said "The setting of the target date for the decision making of the SMS and KfW IPEX-Bank application for German government export credit project finance cover is the outcome of hard work by the various contributing teams focussed on securing project debt financing for the Company's HPA project. The successful conclusion of project due diligence and the no fatal flaws finding all bodes well for a positive ECA application assessment".

"Altech's project team and our partners have an intense six week period ahead, as we work to finalise all project information ready for submission of the PwC expert opinion report and the application for ECA cover", Mr Tan concluded.

To view figures, please visit:
http://abnnewswire.net/lnk/X55K164B


About Altech Batteries Ltd

Altech Chemical Ltd ASX:ATCAltech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns. 

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

https://twitter.com/altechbatteries https://www.facebook.com/AltechChemicals/ https://au.linkedin.com/company/altechbatteries abnnewswire.com 


Contact

Corporate
Iggy Tan
Managing Director
Altech Batteries Limited
Tel: +61-8-6168-1555
Email: info@altechgroup.com

Martin Stein
Chief Financial Officer
Altech Batteries Limited
Tel: +61-8-6168-1555
Email: info@altechgroup.com