MEO Australia Limited Stock Market Press Releases and Company Profile
Heron South-1 Progress Report No. 15
Heron South-1 Progress Report No. 15

Melbourne, Nov 14, 2012 AEST (ABN Newswire) - MEO Australia Limited (googlechartASX:MEO) (OTCQX:MEOAY) provides the following update in relation to Heron South-1 being drilled in NT/P68, operated by Eni Australia Ltd (Eni).

Since the last report the 178m (7") liner has been cemented in place to 4,255mMDRT*.

The forward plan is to clean out the wellbore prior to installing a 114mm (4 1/2") slotted liner.

Eni has advised that it intends to carry out two separate production tests to determine reservoir productivity and gas composition of the two zones of interest intersected by the well.

In accordance with pre-drilling plans, the well will be plugged and abandoned at the conclusion of production testing.

MEO's CEO and MD Jürgen Hendrich commented on the announcement:

"Eni continues to work diligently towards production testing the two zones of interest. Successful cementing of the 7" liner over the upper zone now paves the way for the 4 1/2" slotted liner to be installed across the lower zone. We eagerly await the commencement of production testing."

*Metres Measured Depth below Rotary Table


Contact

MEO Australia Limited
T: +61-3-8625-6000
F: +61-3-9614-0660
E: admin@meoaustralia.com.au
WWW: www.meoaustralia.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 5) (Last 30 Days: 18) (Since Published: 1555)