Genex Power Ltd Stock Market Press Releases and Company Profile
Construction Commences at Kidston Hydro Project
Construction Commences at Kidston Hydro Project

Sydney, April 28, 2021 AEST (ABN Newswire) - Genex Power Limited (googlechartASX:GNX) is pleased to announce that, further to its announcement of Project Document Contractual Close on 31 March 2021, it has today issued Notice to Proceed under two key construction contracts to formally commence construction of the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro or Project).

This follows the issuance of Notice to Proceed to Powerlink for the 275kV transmission infrastructure works, on 31 March 2021.

Genex is pleased to advise that it has today issued Notice to Proceed under the Engineering, Procurement and Construction (EPC) contract with a joint venture of McConnell Dowell Constructors (Aust.) Pty Ltd and John Holland Group Pty Ltd (MDJH JV) for the Project. The EPC scope includes dam construction, underground and waterway civil works and the full powerhouse fit-out (including supply and installation of all electromechanical equipment).

In addition, Genex has issued Notice to Proceed under the design and construct (D&C) contract with Energy Solutions Pty Ltd trading as Beon (Beon) for the surface connection assets. The D&C scope includes a new substation at Kidston to connect into the Powerlink transmission line, and new 275kV transmission infrastructure to connect from the substation to the EPC works.

The issuance of Notice to Proceed under these two contracts formally commences the construction program for the Project, which is expected to take 3.75 years to complete.

Concurrent with commencement of activities under the EPC and D&C contracts, Genex is also ramping up its site activities with the following works:

- Continuation of refurbishment works for the Oaks Rush accommodation village, which is being utilised as the Project construction camp;

- Completion of the airstrip upgrades to facilitate fly-in fly-out operations for construction personnel;

- Continuation of the communications infrastructure upgrades; and

- Commencement of upgrade works on the fresh water supply line from the Copperfield Dam.

With construction now commencing, Genex is looking to formally close-out the financing arrangements, with financial close remaining scheduled to occur in mid-May 2021, following the Extraordinary General Meeting on 29 April 2021.

Commenting on today's announcement, Genex CEO James Harding stated: "I am delighted to have today formally commenced construction of our flagship Kidston Pumped Storage Hydro Project, with the issuance of Notice to Proceed to McConnell Dowell - John Holland joint venture for the construction of the pumped storage hydro plant and dam infrastructure, and to Beon for the ancillary surface connection works at Kidston.

With activity steadily ramping up at site, Genex is now firmly focussed on the delivery of this Project through the construction phase, with commissioning and operations to commence in late 2024. We look forward to updating the market as these activities progress over the coming months."


About Genex Power Ltd

Genex Power Ltd ASX:GNXGenex Power Limited (ASX:GNX) is focused on developing a portfolio of renewable energy generation and storage projects across Australia. The Company's flagship Kidston Clean Energy Hub, located in north Queensland, will integrate large-scale solar generation with pumped storage hydro. The Kidston Clean Energy Hub is comprised of the operating 50MW stage 1 Solar Project (KS1) and the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro) with potential for further multi-stage wind and solar projects. The 50MW Jemalong Solar Project (JSP) is located in NSW and provides geographical diversification to the Genex Power Limited portfolio. JSP was energised in early December 2020 and commissioning is now underway. Genex is further developing its energy storage portfolio via the early stage development of a 50MW/75MWh standalone battery energy storage system at Bouldercombe in Queensland. With over 400MW of renewable energy and storage projects in development, Genex is well placed as Australia's leading renewable energy and storage company.

https://twitter.com/Genex_Power https://www.facebook.com/genexpowerlimited/ https://www.youtube.com/channel/UC0p4njH5MsRCfphzaZ2XLCA https://www.linkedin.com/company-beta/10858225?pathWildcard=10858225 abnnewswire.com 


Contact

Simon Kidston
Executive Director
Tel: +61 2 9048 8850
Email: sk@genexpower.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 8) (Last 30 Days: 33) (Since Published: 4064)