Palm Valley 12 Drilling Update
Palm Valley 12 Drilling Update

Brisbane, May 10, 2022 AEST (ABN Newswire) - Central Petroleum Limited (googlechartASX:CTP) (googlechartC9J:FRA) (googlechartCNPTF:OTCMKTS) advises that on 9 May 2022, the Palm Valley 12 (PV12) well in OL3, Southwest of Alice Springs in the Northern Territory, had reached a depth of 1,103m at 0600 hrs ACST. In the past week a total of 283m of drilling has occurred reaching the planned total depth for the 17.5" hole section at 1,103m on 5 May 2022.

Consequent to reaching total depth, the 13 3/8" casing has been run and cemented, the blowout preventer and surface equipment has been pressure tested and the well is anticipated to commence drilling ahead in 12 1/4" hole from 10 May 2022.

The PV12 well has two alternate objectives, consisting of a deeper gas exploration target or a shallower gas appraisal lateral that could become a production well. The primary exploration target is the Arumbera Sandstone at an anticipated depth of 3,560m.

The PV12 well is the first of a 2-well drilling program that also includes the Dingo-5 exploration / production well. Both wells are being drilled under joint ventures between Central (50% interest), New Zealand Oil & Gas Limited (googlechartASX:NZO) (35% interest) and Cue Energy Resources Limited (googlechartASX:CUE) (15% interest) and are scheduled to be completed this year.

*To view the location map, please visit:
https://abnnewswire.net/lnk/LQF9ZAR0


About Central Petroleum Limited

Central Petroleum LimitedCentral Petroleum Limited (ASX:CTP) is a well-established, and emerging ASX-listed Australian oil and gas producer. In our short history, Central has grown to become the largest onshore gas producer in the Northern Territory (NT), supplying industrial customers and senior gas distributors in NT and the wider Australian east coast market.

Central is positioned to become a significant domestic energy supplier, with exploration and development plans across 180,000 km2 of tenements in Queensland and the Northern Territory, including some of Australia's largest known onshore conventional gas prospects. Central has also completed an MoU with Australian Gas Infrastructure Group (AGIG) to progress the proposed Amadeus to Moomba Gas Pipeline to a Final Investment Decision.

We are also seeking to develop the Range gas project, a new gas field located among proven CSG fields in the Surat Basin, Queensland with 135 PJ (net to Central) of development-pending 2C contingent resource.

abnnewswire.com 


Contact

Investor and Media Inquiries:
Greg Bourke: +61-478-318-702
Sarah Morgan: +61-421-664-969



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 15) (Last 30 Days: 38) (Since Published: 2884)