Drilling at the Achmmach Tin Project
Drilling at the Achmmach Tin Project

Perth, Feb 27, 2008 AEST (ABN Newswire) - Kasbah Resources Limited (Kasbah)(ASX: KAS) is please to provide this update as to its progress at its Achmmach Tin Project in Morocco. The objectives of the Phase 1 exploration drill programme are to explore near surface conceptual targets to assess the opportunity for shallow open pit tin mining in the eastern end of the project and to verify drilling previously undertaken by ONHYM.

In Phase1, 4,000m of diamond drilling is planned and to date 3,300m have been completed. The remainder of the drilling, assaying and analysis of results which are required to complete the Phase 1 programme will be completed in the March quarter.

Kasbah drill holes (AD001 - AD008) were following up high grade surface rock chip results and testing conceptual near surface targets outside the principal target horizon. Assessment of this structural model is ongoing and continually reviewed as additional results become available.

Subsequent drilling in this area has returned to systematic testing of the principal target horizon with early success in drill holes AD009 and AD010 which included intercepts in AD009 of:

- 1m @ 1.9% Sn from 52m

- 3m @ 1.2% Sn from 93m

- 1m @ 1.4% Sn from 140m

- 1m @ 2.4% Sn from 145m

- 3m @ 1.8% Sn from 200m (including 1m @ 4.08% Sn from 200m)

- 2m @ 1.19% Sn from 205m.

And from AD010:

- 12m @ 0.57% Sn from 74m (including 1m @ 1.45% Sn from 78 m)



ACHMMACH TIN PROJECT - SIGNIFICANT DRILL HOLE TIN INTERCEPTS
------------------------------------------HOLE #  FROM       TO      INTERVAL  ASSAY        (METRES)  (METRES)  (METRES)  % Sn------------------------------------------AD001                                NSR AD002                                NSR AD003                                ARAD004                                NSRAD005                                NSRAD006                                ARAD007                                ARAD008                                ARAD009     52        53         1     1.93AD009     82        83         1     0.67AD009     93        96         3     1.25AD009     140       141        1     1.39AD009     145       146        1     2.43AD009     160       161        1     0.51AD009     200       203        3     1.80including 200       201        1     4.08AD009     205       207        2     1.19AD009     211       212        1     0.56AD010     54        55         1     0.50AD010     63        64         1     1.29AD010     70        71         1     0.50 AD010     74        86         12    0.57including 78        79         1     1.45AD010     122       123        1     0.51AD011                                AR            AD012                                SAD013                                ARAD014                                S------------------------------------------Significant defined as ≥ 1m and ≥ 0.5% Sn with ≤ 1m internal dilutionNSR - no significant results AR - awaiting results S - sampling in progressSn % - determined by XRF / ICP-AES method Sample preparation and analyses by Reminex Lab, Marrakech, MoroccoReminex are certified ISO9001 by SGS and ISO17025 by CofracAD001-11 samples were HQ1/4 core, subsequent sampling was HQ1/2 core
Managing Director of Kasbah Resources, Wayne Bramwell said:

"These are the preliminary results from the first stage of a much larger exploration programme at our flagship Achmmach Tin Project. This system is large and requires a detailed, systematic approach to build on the foundation commenced by ONHYM. The remainder of the drilling, assaying and analysis of results which are required to complete the Phase 1 programme will be completed in the March quarter.

The early success in defining high grade hits in untested areas around AD009 and AD010 gives us confidence in the potential of this under-explored tin system. The hard work of unlocking the key geological structures, true size and potential of this project has only just begun and Kasbah's understanding of the project is in its infancy and is growing daily."

Contact

Wayne Bramwell
Managing Director
Phone: +61 8 9463 6651

Peter Youd
Chief Financial Officer
Phone: +61 8 9463 6651
info@kasbahresources.com


ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 3) (Last 30 Days: 18) (Since Published: 2910)