Adelaide, Nov 12, 2008 AEST (ABN Newswire) - Beach Petroleum Limited (ASX:BPT)(PINK:BEPTF) announce the drilling report for the week ending ending 12 November, 2008 are attached.

Highlights of the week's activities include:

Cooper/Eromanga Oil

In areas operated by Santos, one well is in progress (Watson-3, Beach 38.50%).

Beach Petroleum Operated Cooper / Eromanga Exploration

The Ensign 30 drill rig is being moved from the Brownlow-1 gas discovery to Canunda-1, (PEL 106FI, Beach earning 50.00%) which is scheduled to spud on or about 14 November. The well, located 11.5 km to the north of Brownlow-1, is targeting liquids rich Patchawarra Formation gas within a fault dependant closure on the western margin of the highly productive Patchawarra Trough.

Bass Basin - Offshore Tasmania: PeeJay-1 (T/39P)

Rig repairs have been completed and the West Triton jack-up rig is now back on location at PeeJay-1, currently jacking up. (Beach earning 50.00%).
----------------------------Well            Participants----------------------------PeeJay-1        BPT*    50.00%  T/39P           BEN     50.00%  Oil Exploration                 Bass Basin, Tas.                ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 (AEST) 12/11/2008          Upper Eastern Depth:                                          View GroupOperation:      Jacking up on location .                                        after completing rig repairs  ----------------------------Well            Participants----------------------------                                   Canunda-1       BPT*    50.00%  PEL106          DLS     50.00%  (Farmin Block)                  Gas Exploration                 C/E Basin, SA---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0800 (CST) 12/11/2008           Patchawarra FmDepth:                          Operation:      Rigging up.                     Progress:----------------------------Well            Participants----------------------------Vega-3          BPT     23.20%  PL 131          STO*    60.06%  Gas Development ORG     16.74%  C/E Basin, QLD                  ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 12/11/2008       Toolachee FmDepth:          1695m                           Patchawarra FmOperation:      Drilling ahead in the Murta Fm.                 Progress:       1695m   ----------------------------Well            Participants----------------------------Watson-3        BPT     38.50%  PL 24           STO*    55.50%  Oil Development IOR     2.00%            C/E Basin, Qld  DLS     2.00%                   AGF     2.00%                   ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 12/11/2008       Hutton Sst    Depth:          1674m (TD)                      Basal JurassicOperation:      Pulling out of hole to run wireline logs.                              Progress:       1659m                                                   --------------------------------COAL SEAM GAS PROJECTS          Location            Participants--------------------------------Pl 198               BPT     40%     Coal Seam Develop't  AOE*    60%     Surat  Basin, QLD                       --------------------------------------------------------------------Well         Depth       Operation: 0600hrs (EST) 12th November 2008--------------------------------------------------------------------Bora Creek 2    288m      Completing wellGlenburnie 3    70m       Drilling ahead in main holeTipton-139      537m (TD) Drilling production section to TD.* Operator (s)  Secondary Targets         BPT  Beach Petroleum Ltd       STO  Santos Limited            AOE  Arrow Energy NL              ORG  Origin Energy Resources LTD  AGF  Australian Gas Fields LTD    BEN Benaris Petroleum N.V                                 DLS Drillsearch Energy         IOR Inland Oil Resources 

Contact

Reg Nelson
Beach Petroleum
08 8338 2833

Mark Lindh
Adelaide Equity
0414 551 361

Ian Howarth
Farrington National
03 9223 2455


ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 4) (Last 30 Days: 9) (Since Published: 1501)