Adelaide, Dec 10, 2008 AEST (ABN Newswire) - Beach Petroleum Limited (ASX:BPT)(PINK:BEPTF) announce the drilling report for the week ending ending 10 December 2008

Highlights of the week's activities include:

Beach Petroleum Operated Cooper / Eromanga Exploration

The Ensign 30 rig is currently being moved to Callawonga-5 (PPL 220) after a short delay due to significant rain in the region. Callawonga-5 is the first well of a four well program including two development wells at the Callawonga Oilfield and two oil exploration wells in PEL 92. Interests in PEL 92/PPL 220 are Beach Petroleum Ltd (75.00%) and Cooper Energy Ltd (25.00%).

Cooper/Eromanga Oil Exploration and Development - Santos Operated

In areas operated by Santos, two wells were successful (Gidgealpa-60, Beach 20.21% and Watkins-1, Beach 38.50%) and one well is in progress (Zeus-1, Beach 30.00%).

Beach Operated Offshore Program - South East Australia

The West Triton jack-up rig was unable to successfully jack up at the Spikey Beach-1 well location and the decision has been made to move the rig to the Fermat-1 location. Fermat-1 (Vic/P46, offshore Otway Basin), is the third of Beach Petroleum's planned three well offshore program. Beach, as Operator is currently considering options for a return to Spikey Beach-1 after Fermat-1. Interests in Fermat-1 are Beach Petroleum (50.00%), Mitsui E&P Australia Pty Ltd (25.00%) and Essential Petroleum Resources Ltd (25.0%).

North Shadwan - Egypt: Burtocal Oil Field Appraisal Well

The 'Burtocal' NS394-2B oil field appraisal well reached total depth on 5 December, intersecting a gross oil column of at least 31 metres in good quality Nubia Formation reservoir sands. Well results will now be evaluated in conjunction with interpretation of reprocessed seismic data to assist in the formulation of potential development plans. The well is being plugged and suspended for future re-entry as a potential future oil producer.
------------------------------------Well                    Participants------------------------------------Spikey Beach-1          BPT*    80.00%  T/38P                   CUE     10.00%  Oil Exploration         EL      10.00%  Bass Basin, Tas.                        ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 (AEST) 10/12/2008          Upper Eastern Depth:          0m                              View GroupOperation:      Unable to successfullly jack up. Rig being moved to                Fermat-1 location in the Otway Basin.  Progress:       0m                      ------------------------------------Well                    Participants------------------------------------Callawonga-5            BPT*    75.00%  PPL 220                 COE     25.00%  Oil Development                         C/E Basin, SA                           ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 (CST) 10/12/2008           Namur SstDepth:          0m                      Operation:      Rig moving onto location.Progress:       0m                      ------------------------------------Well                    Participants------------------------------------ NS394-2B                BPT     20.00%  (Burtocal-2B)           BP*     50.00%  Oil Appraisal Well      TOE     30.00%                      N. Shadwan, Egypt                       ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600hrs (Egypt) 10/12/2008      Nubia SstDepth:          3215mRT (-3128m TVDSS) (TD)     Matulla SstOperation:      Plugged and suspended for re-entery as a potential                future oil producer.         Progress:       304m ------------------------------------Well                    Participants------------------------------------ Watkins-1               BPT     38.50%  PL 35                   STO*    55.50%  Oil Exploration         IOR     2.00%                C/E Basin, Qld          AGF     2.00%                                        DLS     2.00%   ---------------------------------------------------------------Weekly Progress & Summary                     Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 10/12/2008     Hutton SstDepth:          1724m (TD)                    Basal Jurassic (s)Operation:      Well has been cased and suspended as a future Hutton                Sst, Westbourne Fm and Basal Jurassic oil producer.Progress:       435m                    ------------------------------------Well                    Participants------------------------------------Gidgealpa-60            BPT     20.21%  PPL 6                   STO*    66.60%  Oil Appraisal           ORG     13.19%                       C/E Basin, Qld                ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 10/12/2008       Hutton SstDepth:          1891m (TD)                      Operation:      Well has been cased and suspended as a future Namur                Sandstone and Hutton Sandstone oil producer.Progress:       781m ------------------------------------Well                    Participants------------------------------------ Zeus 1                  BPT     30.00%  ATP 259P                STO*    70.00%  Oil Exploration                         C/E Basin, QLD                          ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (AEST) 10/12/2008      Hutton SstDepth:          92m                             Namur Sst  (s)Operation:      Drilling sirface hole           Basal JurassicProgress:       92m                     ------------------------------------Well                    Participants------------------------------------Okotoko-3               BPT     23.20%  PL 83                   STO*    60.06%  Gas Development         ORG     16.74%  C/E Basin, QLD                          ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 10/12/2008       Patchawarra FmDepth:          933m                            Hutton SstOperation:      Drilling ahead in main hole.                   Progress:       933m                    --------------------------------COAL SEAM GAS PROJECTS          Location            Participants--------------------------------PL 198              BPT     40%        Coal Seam Develop't AOE*    60% Surat  Basin, QLD --------------------------------------------------------------------Well         Depth       Operation: 0600hrs (EST) 10th December 2008--------------------------------------------------------------------Tipton- 144     526m    Drilling ahead  towards total depth
* Operator
(s) Secondary Targets
ASX:BPT Beach Petroleum Ltd
ASX:STO Santos Limited
ASX:TOE TriOcean Energy
ASX:AOE Arrow Energy NL
ASX:ORG Origin Energy Resources LTD
ASX:AGF Australian Gas Fields LTD
BP BP Exploration (Delta)
ASX:CUE Galveston Mining Corp
ASX:DLS Drillsearch Energy
ASX:IOR Inland Oil Resources
ASX:COE Cooper Energy Resources
EL Exoil Limited

Contact

Reg Nelson
Beach Petroleum
08 8338 2833

Mark Lindh
Adelaide Equity
0414 551 361

Ian Howarth
Farrington National
03 9223 2455


ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 2) (Last 30 Days: 10) (Since Published: 1702)