Adelaide Energy Limited (ASX:ADE) Holdfast-1 Weekly Drilling Report Ended 1 Feb 2011
Adelaide, Feb 1, 2011 AEST (ABN Newswire) - Adelaide Energy Limited (
ASX:ADE) is pleased to release Holdfast-1 weekly drilling report ended 1 Feb 2011.
- Well name: Holdfast-1
- Permit: PEL 218 (Permian JV)
- Participants: Beach Energy Ltd (
ASX:BPT) (
PINK:BEPTF) - 90% (Operator); Adelaide Energy Ltd (ADE) - 10%
- Primary targets: Roseneath/Epsilon/Murteree shale/sand/shale sequence ("REM" unit)
- Spud date: 21 January 2011
- Target depth (prognosed): 3625m
- Total depth @ end of current week: 955m
- Total depth @ end of previous week: 776m
- Metres drilled during week: 179m
- Activities during week: Drill 17 1/2" surface hole - run and cement 13 3/8 surface casing at 949.4m
- Current activities: Awaiting crane for BOP installation - prepare 12 1/4" drilling assembly
- Planned activities: Install and test BOPs - commence 12 1/4" intermediate hole
- Other comments: Light rain during week - some hindrance to operations
For the complete Adelaide Energy Limited announcement including chart, please refer to the following link:
http://www.abnnewswire.net/media/en/docs/65128-ASX-ADE-181667.pdf
Contact
Carl Dorsch
Managing Director
Adelaide Energy Limited
Mob:+61-0400-508-088
Email: c.dorsch@adelaideenergy.com.au
Neil Young
Chief Commercial Officer
Adelaide Energy Limited
Mob: +61-0417-850-245
Email: neil.young@adelaideenergy.com.au
http://www.adelaideenergy.com.au
| ||
|