Beach Energy Limited Stock Market Press Releases and Company Profile
Monthly Drilling Report - March 2013
Monthly Drilling Report - March 2013

Adelaide, April 3, 2013 AEST (ABN Newswire) - Beach Energy Limited (googlechartASX:BPT) (googlechartPINK:BCHEY) announce the monthly drilling report for March 2013 with the following highlights. Halifax-1 flowed gas at up to 4.2 MMscf/d, 700 metres of Murteree Shale section cased in Holdfast-2 and Kalladeina-2 marks resumption of oil exploration on Western Flank.

AUSTRALIA

Operated Cooper Basin Unconventional Gas Program

PEL 218 (Beach 100%)

Dashwood-1, the sixth well in the current vertical exploration program in PEL 218 of up to eight wells, is drilling ahead in the Nappamerri Group at 2,533 metres.

The first horizontal well, Holdfast-2, has been cased and suspended after penetrating approximately 700 metres of the Murteree Shale, of which almost 600 metres constituted the horizontal section of the well. Holdfast-2 has the largest step-out from the surface location of any Cooper Basin horizontal well to date at 988 metres which represents a significant achievement for the first well of its type in this unconventional program. The well design of the next horizontal well, Encounter-2, is currently under review and will incorporate improved understandings from the drilling of Holdfast-2.

The horizontal section will be fracture stimulated as part of the next batch stimulation phase. The optimal number of stages for this lateral is currently being assessed.

ATP 855P (Beach 60%)

The flowback of the Halifax-1 well was initially choked back due to temperature constraints on surface equipment. After two weeks of flowing back gas and stimulation fluid, a rate of 4.2 MMscfd was recorded. Due to heavy localised rains, the well was shut-in early March and choked back for the major part of the month. Currently the well is flowing unconstrained at a rate of 1.8 MMscf/d.

Operated Cooper Basin Oil Exploration - Penola Trough (Beach farming-in to earn 35%)

Sawpit-2, an exploration well in South Australia's PEL 495, reached a total depth of 2,585 metres and encountered minor shows in the Upper Sawpit Shale and basement. The well was plugged and abandoned. A total of 56 metres of core from shales in the Casterton Formation and Lower Sawpit Shale was recovered, with detailed analyses of these samples expected to take several months.

Operated Cooper-Eromanga Oil - Western Flank

Oil drilling has re-commenced in the Western Flank region with the spudding of the Kalladeina-2 exploration well in PEL-91 (Beach 40%). At the time of reporting, the well was drilling ahead in the Namur Sandstone. Oil exploration, appraisal and development drilling in Beach-operated permits on the Western Flank is expected to continue for several months.

Santos Operated Cooper Basin Oil and Gas Exploration and Development

The gas development program in the Baryulah field in Queensland (Beach 23.20%) has been completed, with the final well, Baryulah-14, cased and suspended for future production. The rig has now moved to drill the Lepard-2 gas development well, which is currently preparing to drill ahead having set surface casing.

On the South Australian side of the Cooper Basin (Beach 20.21%), the Burke-12 and Goyder-6 wells were cased and suspended as future gas producers, while Cowralli-22 is drilling ahead toward a Patchawarra development target. Cowralli-22 is the first of sixteen development wells planned for the Cowralli field that will use deviated drilling from a single multi-well surface pad. This is designed to pioneer engineering and cost savings in this area.

The Achilles-1 oil exploration well (Beach 30%) was plugged and abandoned after failing to intersect hydrocarbons.

INTERNATIONAL

Kuwait Energy Operated - Abu Sennan Concession, Egypt (Beach 22%)

The ASC-1X exploration well reached a total depth of 4,282 metres within the Kharita Formation. The well has been cased and is being prepared for a testing program to evaluate oil shows identified during drilling.

For the full tables and diagrams, please visit:
http://media.abnnewswire.net/media/en/docs/ASX-BPT-728807.pdf

Contact

Beach Energy Limited
T: +61-8-8338-2833
F: +61-8-8338-2336
WWW: www.beachenergy.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 4) (Last 30 Days: 20) (Since Published: 3742)